Terafab deep dive
SpaceX × Tesla chip fab · data as of October 7, 2026

SpaceX · Tesla · xAI (expected user)

Terafab: a vertically integrated AI-chip fab in Grimes County, Texas

Musk's plan to put logic, memory, advanced packaging, test and masks under one roof, so Tesla, SpaceX and xAI stop depending on outside foundries for AI chips. Unveiled in Austin in March 2026. Tesla runs a ~$3B research fab at Giga Texas, while SpaceX leads the scaled-up Grimes County complex, which broke ground in August 2026. Intel is the process partner. Phase 1 wafer capacity and the first-silicon date have not been disclosed.

ConfirmedReportedClaim / targetUnverifiedMissedNot yet

No official site photos or renderings with a clear reuse license were found, so this page has no images.

Initial phase investment
~$16.8B

SpaceX/Tesla announcement, Aug 2026

SpaceXConstructConnect
Full buildout (filing)
Up to $119B

$55B first phase in May county filing

CNBC
Site footprint
>100M sq ft

Grimes County, TX: >1,700 football fields

SpaceXSpectrum News 1
Jobs
≥3,000

Initial phase commitment

ConstructConnect
Compute goal
1 TW / yr

Musk: 100–200 GW terrestrial + ~1 TW in space

Tom's HardwareTechCrunch
Process partner
Intel 14A

Intel joined Apr 7; reaffirmed Oct 7

TechCrunchTom's Hardware via Yahoo FinanceTom's Hardware
First operations
Late 2027 (limited)

SpaceX expectation; tax incentives start 2029

Spectrum News 1ThePCEnthusiast
Phase 1 wafer capacity
Not disclosed

Musk's earlier goal: 100k → 1M wafer starts/mo

TechSpot

Scope: what Terafab is supposed to make

Musk claims vs. filed facts
What's under one roof
Logic · memory · packaging · test · masksClaim / target
Tom's Hardware
Chip family 1
Edge inferenceClaim / target
For Tesla vehicles, Cybercab and Optimus
Tom's HardwareSpaceX
Chip family 2
High-power, space-hardenedClaim / target
For orbital AI data centers
Tom's HardwareSpaceX
Process node
Intel 14A (planned)Claim / target
Musk on Apr 22: 14A 'not yet totally complete'. 2nm-class was cited at launch
Tom's Hardware via Yahoo FinanceSiliconANGLE
Tesla research fab
~$3B · Giga TexasClaim / target
'A few thousand wafers per month'; broke ground Apr 2026
Tom's Hardware via Yahoo Finance
Scaled fab
SpaceX-led · Grimes CountyConfirmed
'SpaceX is going to take care of the initial phase of the scaled-up Terafab'
Tom's Hardware via Yahoo FinanceSpaceX
Location
Near Gibbons Creek ReservoirConfirmed
Off Hwy 30, ~15–20 mi from Texas A&M
Houston ChronicleKBTX
Expected users
Tesla · SpaceX · xAIReported
Spectrum News 1
Wafer starts (target)
100k / mo → 1M / moClaim / target
Musk's Nov 2025 goal; no Phase 1 figure published
TechSpot
Does it make AI5 / AI6?
No (per current plans)Confirmed
AI5/AI6 go to Samsung (Taylor) and TSMC; Terafab chips are unnamed
Tom's HardwareSeoul Economic Daily

Partners & suppliers

Who does what
IntelConfirmed

Process technology partner (14A). Joined Apr 7, 2026; CEO Lip-Bu Tan said on Oct 7 that Intel remains involved.

TechCrunchTom's Hardware
TSMCClaim / target

Musk confirmed talks in late Sep. On Oct 7 he said TSMC will not run Terafab and might only sublease part of it.

CNATom's Hardware
SamsungConfirmed

Not a Terafab partner. Its $16.5B deal (Jul 2025) covers AI6, and trial AI5 production at Taylor started Sep 2026.

ReutersSeoul Economic Daily
Micron / TSMC / Samsung supplyClaim / target

Musk said Tesla will keep buying chips and memory from existing suppliers.

Tom's Hardware
State of TexasReported

$30M Texas Enterprise Fund grant; $1.66B local tax abatement.

ConstructConnectKBTX

Claims vs reality

Cost, timing, output, control
ItemPromised / targetReality (Oct 7, 2026)Status
Cost

~$20B reported at launch (some outlets said $25B)

Tom's HardwareSiliconANGLE

$16.8B initial phase; county filing shows $55B first phase and up to $119B full buildout

ConstructConnectCNBC
Confirmed
Timeline

No timeline given at launch

Tom's Hardware

Phase 1 construction 2026–2028; limited operations expected toward end-2027

ThePCEnthusiastSpectrum News 1
Not yet
Who runs it

Musk: 'we will build and run the fab'

CNA

SpaceX leads scaled phase; Intel supplies process tech; TSMC sublease floated only

Tom's Hardware via Yahoo FinanceTom's Hardware
Claim / target
Output

1 TW/yr of compute; 100k → 1M wafer starts/mo

TechCrunchTechSpot

No wafer capacity disclosed for Phase 1; research fab: 'a few thousand wafers per month'

Tom's Hardware via Yahoo Finance
Not yet
Node readiness

Leading-edge (2nm-class / Intel 14A)

SiliconANGLETechCrunch

Intel 14A 'not yet totally complete' (Musk, Apr 2026)

Tom's Hardware via Yahoo Finance
Not yet
Transparency

Public incentive process

CNBC

SpaceX sued the Texas AG and Grimes County to withhold parts of its application file

KBTX
Reported
CostConfirmed

Target: ~$20B reported at launch (some outlets said $25B)

Tom's HardwareSiliconANGLE

Reality: $16.8B initial phase; county filing shows $55B first phase and up to $119B full buildout

ConstructConnectCNBC
TimelineNot yet

Target: No timeline given at launch

Tom's Hardware

Reality: Phase 1 construction 2026–2028; limited operations expected toward end-2027

ThePCEnthusiastSpectrum News 1
Who runs itClaim / target

Target: Musk: 'we will build and run the fab'

CNA

Reality: SpaceX leads scaled phase; Intel supplies process tech; TSMC sublease floated only

Tom's Hardware via Yahoo FinanceTom's Hardware
OutputNot yet

Target: 1 TW/yr of compute; 100k → 1M wafer starts/mo

TechCrunchTechSpot

Reality: No wafer capacity disclosed for Phase 1; research fab: 'a few thousand wafers per month'

Tom's Hardware via Yahoo Finance
Node readinessNot yet

Target: Leading-edge (2nm-class / Intel 14A)

SiliconANGLETechCrunch

Reality: Intel 14A 'not yet totally complete' (Musk, Apr 2026)

Tom's Hardware via Yahoo Finance
TransparencyReported

Target: Public incentive process

CNBC

Reality: SpaceX sued the Texas AG and Grimes County to withhold parts of its application file

KBTX

Milestone timeline

Oldest first
  1. Nov 2025Terafab idea floatedClaim / target

    At Tesla's annual meeting Musk talked of a fab starting at 100k wafer starts/month and scaling to 1M.

    TechSpot
  2. Mar 21, 2026Unveiled in AustinConfirmed

    Livestream from Seaholm: logic, memory, packaging, test and masks in one place; ~$20B reported; no timeline.

    Tom's HardwareSiliconANGLE
  3. Apr 7, 2026Intel signs onConfirmed

    Intel to help 'accelerate Terafab's aim to produce 1 TW/year of compute'.

    TechCrunch
  4. Apr 22, 2026Structure set on Q1 callConfirmed

    ~$3B Tesla research fab at Giga Texas (a few thousand wafers/mo); SpaceX takes the initial scaled phase; Intel 14A.

    Tom's Hardware via Yahoo Finance
  5. May 6, 2026Grimes County filingConfirmed

    $55B first phase, up to $119B full buildout; hearing June 3.

    CNBC
  6. Aug 6, 2026Groundbreaking announcedConfirmed

    SpaceX and Tesla commit ~$16.8B initial phase, >100M sq ft, ≥3,000 jobs; $30M state grant.

    SpaceXConstructConnect
  7. Sep 10, 2026Records lawsuitReported

    SpaceX sued AG Paxton and Grimes County to block release of parts of its Terafab application file (the tax deal itself is public).

    TeslaNorthKBTX
  8. Sep 28–29, 2026Site clearing visibleReported

    Burn piles and clearing along Hwy 30; footprint >1,700 football fields, more than 3 miles across.

    Spectrum News 1KBTX
  9. Oct 7, 2026'ZERO doubt' on TSMCConfirmed

    Musk: Tesla/SpaceX will build and run the fab; TSMC could at most sublease. Intel says it is still involved.

    CNATom's Hardware

Risks & open questions

Cost dwarfs early estimatesReported

Estimates went from ~$20B at launch to $55B for the first phase and up to $119B. UBS put Musk's initial 100k-wafer target at ~$30B.

Tom's HardwareCNBCTechSpot
Process maturityClaim / target

Terafab depends on Intel 14A, which Musk said in April was not yet complete.

Tom's Hardware via Yahoo Finance
Who paysReported

SpaceX is funding the scaled phase. Deals between Musk companies need approval from both boards.

Tom's Hardware via Yahoo Finance
DisclosureReported

SpaceX is in court to withhold parts of its Terafab application file from public-records requests.

KBTX

Musk on Terafab

Verbatim, with source
“We either build the TeraFab, or we don't have the chips, and we need the chips, so we build the TeraFab.”
Elon Musk · Mar 21, 2026 · Launch event, Austin
Tom's Hardware
“Probably a hundred to two hundred gigawatts a year of terrestrial chips, and probably on the order of a terawatt of chips in space.”
Elon Musk · Mar 21, 2026 · On long-run demand
Tom's Hardware
“No, we will build and run the fab. Let there be ZERO doubt about that. Maybe TSMC subleases part of the Terafab if they want, but nothing more than that.”
Elon Musk · Oct 7, 2026 · Post on X, responding to TSMC reports
CNA
“SpaceX is going to take care of the initial phase of the scaled-up Terafab.”
Elon Musk · Apr 22, 2026 · Tesla Q1 2026 call
Tom's Hardware via Yahoo Finance

Latest news

Newest first
  1. Oct 7, 2026Musk rules out TSMC running TerafabConfirmed

    A sublease is possible; Intel reaffirms its 14A role.

    CNATom's Hardware
  2. Sep 29, 2026Transparency questions mountReported

    $1.66B tax break; records requests; SpaceX lawsuit.

    KBTX
  3. Sep 28, 2026Plant 'takes shape' in Grimes CountyReported

    SpaceX expects limited operations toward end-2027.

    Spectrum News 1
  4. Sep 16, 2026Samsung trial-produces AI5 in TaylorReported

    Tesla's next chips are still made outside Terafab.

    Seoul Economic Daily
  5. Aug 6, 2026SpaceX: breaking ground on TerafabConfirmed

    $16.8B initial phase.

    SpaceX

Not disclosed / unverified

Not filled in on purpose
  • Phase 1 wafer starts per month and the process node in the first production module
  • First-silicon date. Only 'limited operations toward end of 2027' (SpaceX) and incentives starting in 2029
  • Names or specs of Terafab-made chips (AI5/AI6 are made at Samsung/TSMC)
  • How capex is split between SpaceX, Tesla and xAI
  • Whether TSMC will sublease space (Musk floated it Oct 7)

Sources

18 references · open in new tab
  1. 1.Breaking Ground on Terafab in Texas · SpaceX · Aug 6, 2026
  2. 2.SpaceX, Tesla Terafab chip plant near College Station: what to know · Houston Chronicle · Aug 7, 2026
  3. 3.SpaceX, Tesla set $16.8B initial investment for Texas Terafab · ConstructConnect · Aug 7, 2026
  4. 4.Musk outlines Tesla-SpaceX Terafab in Austin · TechSpot · Mar 23, 2026
  5. 5.Musk unveils $20 billion TeraFab — targets a terawatt of annual compute · Tom's Hardware · Mar 22, 2026
  6. 6.Musk announces Terafab to manufacture chips for space-based AI · SiliconANGLE · Mar 22, 2026
  7. 7.Intel signs on to Musk's Terafab chips project · TechCrunch · Apr 7, 2026
  8. 8.Terafab to use Intel 14A; Tesla pilot line, SpaceX volume (Q1 call) · Tom's Hardware via Yahoo Finance · Apr 22, 2026
  9. 9.Terafab could cost up to $119 billion, filing shows · CNBC · May 6, 2026
  10. 10.Terafab Phase 1 construction 2026–2028 · ThePCEnthusiast · Aug 11, 2026
  11. 11.Terafab semiconductor plant takes shape in Grimes County · Spectrum News 1 · Sep 28, 2026
  12. 12.Terafab site takes shape as Musk's companies face transparency questions · KBTX · Sep 29, 2026
  13. 13.SpaceX sues over Terafab application file, not the public tax deal · TeslaNorth · Sep 10, 2026
  14. 14.Musk says TSMC won't run Terafab AI chip complex · CNA (Reuters) · Oct 7, 2026
  15. 15.Musk rejects TSMC takeover of Terafab; Intel reaffirms 14A role · Tom's Hardware · Oct 7, 2026
  16. 16.Tesla-Samsung $16.5 billion chip supply deal · Reuters · Jul 28, 2025
  17. 17.Samsung starts trial production of Tesla AI chips in Texas · Seoul Economic Daily · Sep 16, 2026
  18. 18.Musk confirms AI5 and AI6 will be made at Samsung and TSMC · Tom's Hardware · 2025